Day 9 - we got the foam insulation around the perimeter of the new floor, and the new back room is really taking shape today. The view from the back door will be perfect.
Tuesday, May 16, 2023
Sunday, May 14, 2023
Day 6: Concrete Pour
Today we cleaned up the driveway, to make way for the concrete truck, and the pour of the remaining foundation walls went well.
Day 5: Tarp & Forms
We have no rain in the forecast, the weather is cooperating beautifully, but we are tarped just in case. Most of the siding has been removed, and the concrete forms were being completed for the pour coming on Saturday.
I added power and a light, so that we can still work up there, and it is SO COOL, except that is a SAUNA up there! I have yet to measure the temperature...
Day 4: Floor Ply is going down...
Most of the floor ply is down, except for near the edges, where we need to take care of some insulation and plumbing rough-in before it gets closed.
Day 3 - Floor Trusses are on!
Day 2 was spent leveling and cleaning up all the debris to have a flat surface to work on, and the bin got picked up. Bye-bye roof.
Day 3: the floor trusses were put on, up to the end of the existing house, but not including the new back addition.
facing North:
facing South:
Week 4 - Walls are going up! It's getting pretty exciting, and again, at the end of the week, we got tarpped just in time for the Frida...
-
Week 3 - some less visible work being done, like plumbing rough-in, and taking off 2 layers of old siding! We are all tarpped and ready for...
-
Day 7 was our day of rest. Day 8, the forms were removed, and the back room has gained a new wall.